Wednesday, April 25, 2007

Laying of tiles..

This week, according to the schedule verbally conveyed to us, the workers will start laying down the tiles in our flat..

So I went to take a peek of the laying of the floor tiles..

Status:
  • Living room: around 50% is already covered with tiles
  • Dining room area is fully covered.
  • Study room floor is still not done yet.
  • The bedroom: HDB has not started on the cement screeding yet.

Whoops.. they dismantled the main door..

Formation of the cement base for the kitchen cabinet

There's still some wet cement at the area near the balcony so I wasn't able to take a close picture of the outdoor tiles.

Looks like they've finished laying the outdoor tiles at our balcony..
A view from the study room.. still unfinished..

Skirting isn't done yet. We told our ID that we wanted to have wood skirting. hopefully it'll turn out good.

It was a quick visit.. probably spent 30 mins there..
I can't wait to see when the tiles are completed..