Tuesday, May 1, 2007

Homogenous tiles laid .. electrical works starting.. bathroom accessories bought..

Found sometime to visit the unit during the Labor Day break..

The tiling for the living/dining and study room has been completed.
Cement screeding for the bedrooms is still not done yet.

Close up pictures of our homogenous tiles:

And also .. the electrical works have started..

Wires hanging down everywhere..

View from the main door
View from the balcony..

We had a very busy weekend to visit lighting shops, air-con contractor, and looking for bathroom accessories.

Managed to finalize the air-con selection.
By the way, we went all the way to Jalan Kayu to view the air conditioner showroom (Long Heng Aircon design ph: 6556 4408 - Eddy)
We finally got to taste the famous Jalan Kayu prata.

Anyway, back to reno stuffs..

We went to a shop in Geylang (Universal Union ph: 67433852 - Irene) and bought all the necessary bathroom accessories: taps, mixer, mirror, shower heads..

Combined pictures of the items we purchased..

Next on the list.. lights and lamps..